1 Reply Latest reply on May 5, 2015 1:17 PM by James Wright

    Split Primary Underground at transformer locations - mass update?

    Sunil Gupta

      Dominion planning and reliability want to split underground primary segments at transformer locations.

      It can be configured for new features using ARCFM configurations. My question is about existing primary UGs.

      How to split the existing features at transformer locations in batch mode? Dominion is still running on 9.3.1.